Slideshow image
Slideshow image
nav image
nav image
While more incremental progress has been made in the last week, there are two big items we're waiting for completion on:
  • Railings: shop drawings were completed and shared with our engineer for review and approval. Significant revisions have been requested by our engineer. This will require revised shop drawings and re-submission for approval. Fabrication and installation will follow approval of the shop drawings. As a result, our completion timeline is August, with the risk of pushing into September, as the entrance, sidewalks and ramps cannot be cleared for use until these steps are completed. 
    • As mentioned previously, the FBC team is in regular conversation with our engineer and the project manager from Associated Paving. All appropriate pressure is being applied to see this project through the finish line. 
  • Clean up of curb markings (orange spray paint, scuff marks from construction) 
  • Repair to west entrance bottom door trim following completion of walkway pavers. 
Again, a special thanks to the Building and Grounds team for taking on the task of regularly watering the perimeter of the parking lot.
Our continued collective faithfulness in prayer for this project is required. Thank you again for yours.
In Him,
Bryan, Ronald and Paul. 
Total Raised to Date: $211,730.45